Dove Fields - Uttoxetter
April 2002 to November 2002

The project involved the remediation of a former Shell Fuel Depot in Uttoxetter. Dunton Contracting designed a scheme which involved the identification of the contamination plumes and the excavation and treatment on site via bioremediation to render the soil suitable for reuse on site as general fill. Exisiting contamination levels of up to 10,000 mg/kg for TPH was found on site and approximately 12,000 m3 of soil was successfully treated to a target level of below 1000mg/kg for TPH. The works were approved and accepted by the Environment agency and independantly warrantied. The result was a successful alternative method to remediation which had significant financial savings for the Client.


 