Haydn Road Nottingham
November 2000 to October 2001
Demolition of a 12,000 sq.m factory and industrial warehouse. Removal of tanks, bases and hardstandings.
Ground
remediation including, recycling 50,000 cu.m of material within an
existing landfill site, screening, selection and disposal of 6,000 cu.m
of waste off site, bulk earthworks and site profiling. Remediation
treatment of 4,000m3 of hydrocarbon contamination.

|